Brightline Passenger Rail Construction Update: Middle River Terrace Area

Brightline Express Train Service Update

BrightlineBrightline began demolishing the existing Middle River Terrace railroad bridges along the FEC railway corridor on Tuesday, October 10, 2017.

Construction on the new bridges will commence with pile driving.

The hours of the construction are 7 a.m. to 7 p.m.

This activity is anticipated to occur through the end of October with the new railroad bridges expected to be completed by the end of November.

To learn more, visit the  Brightline website or telephone 305-520-2105.